New Port Control Tower

Codice opera: P.3023
Titolo progetto: New Port Control Tower
posizione geografica-progetti:
Stato di avanzamento:
  
TFFS 
DD 
ED 
Start Works 
End Works 
Importo complessivo: €19,500,000.00
Attività in corso:
  • , Construction works in progress
Tempistiche:
  • Start Date Preparatory Works, September 2021
  • Start Date, July 2022
  • Completion Date, October 2024
Affidatario:
  • , images/Progetti_logo_affidatari/Cimolai-logo.webp, RTI Cimolai
Annualità: 2020-01-01

The construction of a new Port Control Tower on an artificial island facing the new Marina in the Levante Waterfront. The 60-metre steel tower, designed by Renzo Piano, will watch over the entire area of the Port of Genoa. The project foresees the installation of a perimeter protection wall shoreside.

(Last refresh date 27.02.2023)