Retrofit of quaywalls and upgrades in the passenger port of Genoa
Home
Codice opera: P.3129
Titolo progetto: Retrofit of quaywalls and upgrades in the passenger port of Genoa
posizione geografica-progetti:
Stato di avanzamento:
Lot 1 – Ponte dei Mille
TFFS
DD
ED
Start Works
End Works
Lot 2 – Ponte Doria
Lot 3 – Ponte Eritrea
Lot 4 – Ponte San Giorgio
Importo complessivo: €24,916,784.17
Attività in corso:
Lot 1 - Ponte dei Mille, CONSTRUCTION WORKS COMPLETED (april 2022)
Lot 2 - Ponte Doria, CONSTRUCTION WORKS COMPLETED (may 2021)
Lot 3 - Ponte Eritrea, Works in progress
Lot 4 - Ponte San Giorgio, Works in progress
Tempistiche:
Lot 1 - Ponte dei Mille, CONSTRUCTION WORKS COMPLETED
Lot 2 - Ponte Doria, CONSTRUCTION WORKS COMPLETED
Lot 3 - Ponte Eritrea, Construction Works Start Date: June 2022 | Completion Date: August 2023
Lot 4 - Ponte San Giorgio, Construction Works Start Date: March 2022 | Completion Date: January 2024
Affidatario:
Lot 1 - Ponte dei Mille, images/Progetti_logo_affidatari/Santoro-logo.webp, Giuseppe Santoro srl
Lot 2 - Ponte Doria, images/Progetti_logo_affidatari/TerraCon-logo.webp, Terra.com
Lot 3 - Ponte Eritrea, images/Progetti_logo_affidatari/Agnese_logo.jpg, Dott. Carlo Agnese S.p.A.
Lot 4 - Ponte San Giorgio, images/Progetti_logo_affidatari/Injectosond_Italia_p3129.jpg, Injectosond Italia
Annualità: 2020-01-01
Video:
Video:
:
The project foresees the retrofitting of the Ponte dei Mille, Ponte Eritrea and Ponte S. Giorgio quay walls, with related dredging works, to cater also for the future generation of "World Class" cruise ships. The installation of the three new 300-ton load capacity mooring bollards at the Andrea Doria Cruise Terminal has been completed.