Redevelopment of Christopher Columbus Airport

Codice opera: P.3114
Titolo progetto: Redevelopment of the existing Airport passenger terminal
posizione geografica-progetti:
Stato di avanzamento:
Lot 1 – Embarkation area
  
TFFS 
DD 
ED 
Start Works 
End Works 
Lot 2 – Baggage handling area
  
  
  
  
  
  
Importo complessivo: €937,000.00
Attività in corso:
  • Lot 1 – Embarkation area, WORKS COMPLETED
  • Lot 2 – Baggage handling area, WORKS COMPLETED
Affidatario:
  • Lot 1 – Embarkation area: --, images/Progetti_logo_affidatari/LaCascina_logo.jpg, La cascina costruzioni
  • Lot 2 – Baggage handling area, images/Progetti_logo_affidatari/Sigea-logo.jpg, Sigea
Annualità: 2020-01-01
Video:

Construction of a new facility to the north of the passenger terminal, to be equipped as a temporary embarkation hall during reconstruction works in the terminal building. The project foresees the temporary expansion of the baggage handling hall to accommodate part of the new system.