Redevelopment of Hennebique

Codice opera: P.3119
Titolo progetto: Redevelopment of Hennebique
posizione geografica-progetti:
Stato di avanzamento:
  
TFFS 
DD 
 ED 
Start Works 
End Works 
Importo complessivo: €133,264,841.00
Attività in corso:
  • , Design and reviews. Preliminary construction works stages underway
Tempistiche:
  • Start Date, 1st quarter 2022 (construction site preparation)
  • Completion Date, December 2027
Affidatario:
  • , images/Progetti_logo_affidatari/vitali_logo.jpg, Vitali S.p.a.
Annualità: 2021-01-01

The redevelopment of the historic Hennebique former grain silos, one of the most striking reinforced-concrete buildings of the 20th century, takes shape. Strategically located along Genoa's Waterfront in the Old Port, it overlooks the sea and the city's historical centre and sits adjacent to the Cruise and Ferry Terminal. The plan is to reconvert the building into a major multi-service hub for cruise, tourist and recreational activities.