Project

The project foresees the installation shoreside of electric power converters for the provision of cold ironing at 6 passenger berths in the Port of Genoa to reduce air and noise pollution.

(Last refresh date December 2024)

Project site

Key project data

Project Reference Number P.2946 - On-shore Power Supply at the Cruise and Ferry Terminal
Status
Total cost 20,000,000.00€
Activities Works underway
Timeline Start of works date October 2023
Projected completion date December 2025
Contractor Nidec ASI S.P.A.

Photo Gallery