Project
The project foresees the installation shoreside of electric power converters for the provision of cold ironing at 6 passenger berths in the Port of Genoa to reduce air and noise pollution.
(Last refresh date December 2024)
Project site
Key project data
Project Reference Number | P.2946 - On-shore Power Supply at the Cruise and Ferry Terminal |
---|---|
Status | |
Total cost | 20,000,000.00€ |
Activities | Works underway |
Timeline |
Start of works date
October 2023 Projected completion date December 2025 |
Contractor | Nidec ASI S.P.A. |