Project

The project includes the enhancement of quay load capacity, construction of crane runways, installation of hydraulic and electric power network and new terminal lighting system in the new container terminal.

(Last refresh date February 2025)

Project site

Key project data

Project Reference Number P.3105 - Completion of the new Bettolo Genoa Mediterranean Gateway Terminal
Status
Total cost 9,979,709.27€
Activities Works underway
Timeline Start of works date May 2023
Projected completion date April 2025
Contractor Dott. Carlo Agnese S.P.A.