Project
The project is designed to improve energy efficiency in the Port of Savona, across the installation of photovoltaic systems on the rooftops of warehouses located in the Port of Savona and the connection to the port electrical grid.
(Last refresh date March 2025)
Project site
Key project data
Project Reference Number | P.802-803 - Installation of photovoltaic panels on warehouse rooftops in the Port of Savona |
---|---|
Status | |
Total cost | 11,162,000.00€ |
Activities | Works underway |
Timeline | Start of works date P.802 – 18th November 2024 | P.803 – Timeframe underway Projected completion date 30th June 2026 |
Contractor | RTI CMCI Consorzio stabile Scarl - Iren SpA |