Project
The project is part of an extensive plan, implemented in collaboration with the City of Genoa, to protect the Voltri beach promenade from extreme wave overtopping. It calls for the construction of a rock barrier along the right bank of the River Leira.
(Last refresh date December 2024)
Project site
Key project data
Project Reference Number | P.2931 - Coastal protection of the Voltri Promenade |
---|---|
Status | |
Total cost | 400,000.00€ |
Activities | Works completed |
Timeline | Start of works date April 2021 Projected completion date August 2021 |
Contractor | ZETA S.R.L. |