Project

The project is part of an extensive plan, implemented in collaboration with the City of Genoa, to protect the Voltri beach promenade from extreme wave overtopping. It calls for the construction of a rock barrier along the right bank of the River Leira.

(Last refresh date December 2024)

Project site

Key project data

Project Reference Number P.2931 - Coastal protection of the Voltri Promenade
Status
Total cost 400,000.00€
Activities Works completed
Timeline Start of works date April 2021
Projected completion date August 2021
Contractor ZETA S.R.L.

Photo Gallery