Project

The project foresees the installation of charging points for E-vehicles in 16 parking areas across the Port of Savona-Vado Ligure. Specifically, in Savona the electric vehicle charging devices will be positioned by the BIC building and the Foyer carpark alongside the entrance to the port. Whilst in the Port of Vado-Ligure the facility dedicated to the supply of future charging points will be installed by the PCF and Portgate buildings. The power output of the EV charging devices will range from 22 to 54 kW AC/DC and they will be integrated into the future smart grid funded by the National Recovery and Resilience Plan.

(Last refresh date March 2025)

Project site

Key project data

Project Reference Number P. 800 - The installation of EV charging stations to promote sustainable mobility at the Port of Vado
Status
Total cost 684,000.00€
Activities Works underway
Timeline Start of works date 10th December 2024
Projected completion date 30th June 2026
Contractor CMCI Scarl Consorzio Stabile

Photo Gallery