Project

The plan foresees an upgrade in the rail yard serving the Port of Vado Ligure across the optimisation of the rail track management system. This project, part of a range of rail infrastructure projects., will boost the loading/unloading capacity of the yard and the flexibility of shunting operations, thereby avoiding blocks to the freight railway line terminus on the part of the locomotives.

(Last refresh date June 2025)

Project site

Key project data

Project Reference Number 811 - Vado Railway Gate Upgrade
Status
Total cost 1,653,603.78€
Activities Works underway
Timeline Start of works date December 2024
Projected completion date June 2026 – PNRR target
Contractor IMPRESA PAROLDI GIUSEPPE & C. S.R.L.