"The project calls for the restructuring of the breakwaters in the Ports of Savona and Vado Ligure, which includes raising the height of the cronwall against wave overtopping.
(Last refresh date 06.05.2022)
"The project calls for the restructuring of the breakwaters in the Ports of Savona and Vado Ligure, which includes raising the height of the cronwall against wave overtopping.
(Last refresh date 06.05.2022)
Project Code | P.768 |
---|---|
Project title | Restructuring of the breakwaters in the Ports of Savona and Vado Ligure |
Project status |
Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design,
![]() ![]() |
Project value | €10,150,000.00 |
Current activities | Works in progress |
Commencement date of construction works | 2021-06-04 |
Completion date of construction works | 2023-11-21 |