River defence and engineering works in the port industrial area of Genoa Sestri Ponente and the construction of a new mega dry dock (P.2879)

The first phase foresees the construction of an operational area to the east of the Delta Jetty of the Oil Terminal, and river defence and engineering works along the Molinassi Creek, and thereafter along the Maratto/Monferrato, Chiaravagna, Ruscarolo and Cantarena. The second phase envisages the expansion of the industrial area and the installation of a new 440-metre long dry dock to cater for the construction of mega-ships. Improvement of the landside access to the Genoa Sestri Ponente industrial port area, including the relocation of the railway line.

(Last refresh date 07.06.2022)

Project Code P.2879
Project title River defence and hydraulic engineering works including the improvement of landside access to the industrial port zone of Genoa Sestri Ponente
Project status
PHASE 1 / Molinassi river defence works
  
TFFS 
DD 
ED 
Start Works
End Works 
PHASE 2 / Offshore works – operational platform
  
  
  
  
  
  
PHASE 3 / Offshore works – New mega dry dock
  
  
  
  
  
  
PHASE 4 / Cantarena river defence works
  
  
  
  
  
  
Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design, activity completed  Activity completed activity in progress  Activity in progress  
Project value €636,603,159.57
Current activities PHASE 1 / Molinassi river defence works : Contract awarded. Project underway
PHASE 2 / Offshore works – operational platform: Works underway
PHASE 3 / Offshore works – New mega dry dock: Works underway
PHASE 4 / Cantarena river defence works: Contract awarded. Project underway
Timeline PHASE 1 / Molinassi river defence works : Construction Works Commenced: September 2022 | Completion Date: September 2028
PHASE 2 / Offshore works – operational platform: Construction Works Commenced: April 2021 | Completion Date: May 2023
PHASE 3 / Offshore works – New mega dry dock: Construction Works Commenced: April 2022 | Completion Date: December 2025
PHASE 4 / Cantarena river defence works: Construction Works Commenced: July 2022 | Completion Date: March 2024
Contractor PHASE 1 / Molinassi river defence works Consorzio Stabile; Consorzio integra; ICM; Giuggia
PHASE 2 / Offshore works – operational platform Fincosit; Consorzio Stabile; Consorzio Integra; ICM
PHASE 3 / Offshore works – New mega dry dock RINA Consulting S.p.A.; Consorzio Stabile; Consorzio Integra; Trevi
PHASE 4 / Cantarena river defence works CSI Consorzio Stabile per le infrastrutture
Gallery