New Port Control Tower (P.3023)

The construction of a new Port Control Tower on an artificial island facing the new Marina in the Levante Waterfront. The 60-metre steel tower, designed by Renzo Piano, will watch over the entire area of the Port of Genoa. The project foresees the installation of a perimeter protection wall shoreside.

(Last refresh date 07.06.2022)

Project Code P.3023
Project title New Port Control Tower
Project status
  
TFFS 
DD 
ED 
Start Works 
End Works 
Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design, activity completed  Activity completed activity in progress  Activity in progress  
Project value €19,500,000.00
Current activities Opening of construction site
Timeline Start Date: September 2021
Completion Date: May 2024
Contractor RTI Cimolai
Gallery