New quay development along Ponte dei Mille, with the construction of a new terrace, to cater for the latest generation of ultra-large cruise ships in full safety.
(Last refresh date 05.07.2023)
New quay development along Ponte dei Mille, with the construction of a new terrace, to cater for the latest generation of ultra-large cruise ships in full safety.
(Last refresh date 05.07.2023)
Project Code | P.3133 |
---|---|
Project title | Expansion of Ponte dei Mille Levante |
Project status | Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design,
![]() ![]() |
Project value | €24,000,000.00 |
Current activities | Design project |
Timeline |
Start Date Preparatory Works: :
July 2022 Completion Date: December 2024 |
Contractor | ![]() |
Gallery |