Refurbishment works are soon to be completed at Ponte Eritrea, the final phase of the extensive plan underway to upgrade and retrofit the quaywalls in Genoa’s Sampierdarena freight handling area and...
Emergency
The construction of the new 3-lane viaduct, connecting the Genova-Pra’ motorway exit directly to the container terminal facility, has been completed and is set to improve intermodal mobility at the Port of...
The range of roadworks in progress across the Genoa-Sampierdarena port basin, to improve overall heavy goods vehicle accessibility to the terminal facilities, are near completion. The 167-million euro...
The New Open-Sea Breakwater takes shape as the fast-paced construction of the caissons takes off, with the near-completion of the first of 100 caissons set to form the 6,200 metre port facility.
Genoa, 15 April 2024 – The revolutionary integrated mobility plan, to fast-track connections between Genova City Airport, the railway network and the Passenger Ports of Genoa and Savona, was unveiled today at...
The construction of the first of 100 caissons, which will form Genoa’s New Open-Sea Breakwater, takes shape on board the “Dario” floating dock positioned in the Port of Vado Ligure.
The Ports of Genoa historic headquarters of Palazzo San Giorgio provided the backdrop to the signing ceremony of the concessionary contract between Hennebique s.r.l., the dedicated company composed of Vitali...
The wide-ranging large-scale infrastructure plan is in place at Genoa and Savona's passenger ports and begins to take shape across the cruise terminals. With over 40 million euros already invested to address...
Genoa, 4 March 2024 – Construction has officially started this morning in Genoa on Italy’s first undersea road tunnel, set to become Europe’s largest immersed tunnel. A sophisticated feat of Italian engineering...
Genoa's New Breakwater begins to take shape in the open-sea, with 1 million tons of gravel deposited on the seabed. Construction works proceed on schedule.
Container yard expansion works, in progress since April of last year at the Bettolo Genoa Mediterranean Gateway Terminal in the Sampierdarena Basin, move rapidly ahead.
Work continues offshore on the New Genoa Breakwater, with the second block of columns under construction and 600,000 tons of gravel already deposited on the seabed.
On 30 October construction works commenced in Genoa’s cruise and ferry hub for the installation of new shoreside power facilities to enable passenger vessels, docking at the terminals, to switch off the...
Full planning permission has been granted to the Vitali & Roncello Group which has the mandate to redevelop the Port of Genoa's Hennebique grain silos. At this juncture, by the end of the month, the...
The CLIA European Cruise Week disembarks in Genoa from 11 to 14 March 2024, firmly establishing Genoa as cruise capital of Europe.
The construction of the 850 columns is in its final stages, with a total of 370,000 tons of gravel laid on the seabed. Work on the second block of columns is now set to commence.
The first 720 metres of the 1.8-km Genoa Pra' Dune waterfront promenade now reopens to the public.
Nominated best road infrastructure project, the Papa Bridge wins one of the 16 prestigious awards promoted by the OICE, the Association of Consulting Engineers and Architects, member of Confindustria...
Genoa, 29 June 2023 – Details of the new Undersea Road Tunnel were unveiled today at the landmark headquarters of the Port Authority, Palazzo San Giorgio, alongside the announcement that works have officially...
Western Ligurian Sea Port Authority and Per Genova Breakwater Consortium led by Webuild launch the project in the presence of Italian Infrastructure and Transport Minister Matteo Salvini. The Genoa’s New...