Project

The project calls for the installation of shoreside power facilities for cruise vessels docking at Savona’s Cruise Terminal. The ships will be able to switch off the generators and plug into an electrical power grid to reduce carbon emissions and noise pollution.

(Last refresh date December 2024)

Project site

Key project data

Project Reference Number P.783 - On-shore Power Supply at the Cruise Terminal in Savona
Status
Total cost 10,100,000.00€
Activities Works underway
Timeline Start of works date October 2023
Projected completion date December 2025
Contractor Nidec ASI S.P.A.

Photo Gallery