Ampliamento spazi operativi Calata Bettolo all'80% - Giugno 2024

Ampliamento spazi operativi Calata Bettolo - realizzazione Travi-Slab - Aprile 2024

Ampliamento spazi operativi Calata Bettolo - lavori lotto 1 - Gennaio 2024

Posa prima pietra Calata Bettolo - l’intervento di Signorini

Terminal Bettolo - Ampliamento spazi operativi - aprile 2023

Nuovo Terminal Calata Bettolo - demolizione serbatoi - 18.10.2021
Project
The project includes the enhancement of quay load capacity, construction of crane runways, installation of hydraulic and electric power network and new terminal lighting system in the new container terminal.
(Last refresh date July 2025)
Project site
Key project data
| Project Reference Number | P.3105 - Completion of the new Bettolo Genoa Mediterranean Gateway Terminal |
|---|---|
| Status | |
| Total cost | 10,031,125.36€ |
| Activities | 1st Lot: Works underway |
| Timeline | Start of works date 1st Lot: May 2023 Projected completion date 1st Lot: August 2025 |
| Contractor | 1st Lot: Dott. Carlo Agnese S.P.A. |