Project

The project includes the enhancement of quay load capacity, construction of crane runways, installation of hydraulic and electric power network and new terminal lighting system in the new container terminal.

(Last refresh date July 2025)

Project site

Key project data

Project Reference Number P.3105 - Completion of the new Bettolo Genoa Mediterranean Gateway Terminal
Status
Total cost 10,031,125.36€
Activities 1st Lot: Works underway
Timeline Start of works date 1st Lot: May 2023
Projected completion date 1st Lot: August 2025
Contractor 1st Lot: Dott. Carlo Agnese S.P.A.