Project
The project is designed to improve energy efficiency and environmental sustainability in the Port of Savona, across the installation of photovoltaic systems on the rooftops of warehouses located in the Port of Savona and the connection to the port electrical grid.
(Last refresh date June 2025)
Project site
Key project data
| Project Reference Number | P. 803 - GREEN PORTS PNRR – INSTALLATION OF PHOTOVOLTAIC PANELS ON WAREHOUSE ROOFTOPS IN ZONE 32 ALTI FONDALI IN THE PORT OF SAVONA |
|---|---|
| Status | |
| Total cost | 5,203,000.00€ |
| Activities | Works underway |
| Timeline | Start of works date 16 June 2025 Projected completion date 30 June 2026 |
| Contractor | RTI IREN SMART SOLUTIONS S.P.A. / CMCI S.c.a r.l. Consorzio Stabile |