Project

The project foresees the retrofitting and upgrade of quay walls at Ponte Eritrea. This specific project forms part of the wide-ranging plan, dedicated to the Old Port and Passenger Terminals in Genoa, to equip the terminals with the capacity to accommodate in full safety the future generation of ultra-large ships and to handle added volumes of traffic.

(Last refresh date July 2025)

Project site

Key project data

Project Reference Number P.3129 - Quay Retrofitting at Ponte Eritrea
Status
Total cost 8,183,659.95€
Activities Works underway
Timeline Start of works date June 2022
Projected completion date for quay foot works: December 2025 – Phase 1 works completed in March 2024
Contractor Dott. Carlo Agnese S.p.A.