Project
The project is designed to upgrade rail access from the Genoa Sampierdarena port basin, with the installation of seven 750-metre rail tracks to ensure the safe operation of EU standardised freight cars, the introduction of a new signalling system in compliance with the National Safety Agency requirements and a new electric rail traction system.
(Last refresh date March 2025)
Project site
Key project data
| Project Reference Number | P.3107 - Upgrade of the Fuori Muro Rail Yard |
|---|---|
| Status | |
| Total cost | 74,684,942.00€ |
| Activities | Works underway |
| Timeline | Start of works date March 2025 Projected completion date June 2027 |
| Contractor | RTI Manelli |