Project
The project calls for the installation of a core software platform that manages rail operations and features a computerised tracking system which monitors the movement of rail cars within the terminal. The objective is to improve efficiency, overall productivity and safety in compliance with recent EU legislation. The system interfaces with the national railway network and the adjacent ZI rail facility in Vado Ligure, and has been designed to supply real-time data on the rail terminal, thereby optimising the scheduling of train arrivals at the port. In addition, a reduction in secondary rail operations and loading/unloading processing times contributes to an improvement in the protection of the environment.
(Last refresh date June 2025)
Project site
Key project data
| Project Reference Number | 809 - Vado Ligure Rail Terminal Automation |
|---|---|
| Status | |
| Total cost | 4,893,610.10€ |
| Activities | Preliminary works in construction |
| Timeline | Start of works date June 2025 Projected completion date June 2026 – target PNRR |
| Contractor | R.T.I. PROGRESS RAIL SIGNALING S.p.A./CETIP S.r.l. (RTP PROGRESS RAIL SIGNALING S.p.A./ALL ING. S.r.l.) |