Project

The new breakwater of the Port of Genoa is designed to guarantee direct access to the terminal facilities and a wide turning basin for ultra-large ships to manoeuvre in full safety and, in addition, to cater for future carrier upsizing. Without this new port infrastructure, Genoa cannot expand and risks losing its competitive edge in the global shipping industry.

Project site

Key project data

Project Reference Number P.3062 - New Breakwater of Genoa (Phase A)
Status
Total cost 929,627,097.84€
Activities Works underway
Timeline Start of works date February 2023
Projected completion date November 2026
Contractor Consorzio PerGenova Breakwater