Project

New road infrastructure on-site in the Sampierdarena port area, with smart road-freight dedicated lanes for heavy vehicles which will simultaneously also ease urban traffic congestion. The new roadworks include the installation of the new Ponente smart port gate, construction of the new Ponte del Papa, completion of the via Superba, extension of the major port roadway, new road link between San Benigno and Bettolo container terminal, relocation of the Etiopia port gate, demolition and reconstruction of the Siffredi viaduct and retrofitting of the Pionieri e Aviatori d'Italia (by the Airport) and Ponte dei Mille (by the Cruise Terminal) viaducts.

(Last refresh date January 2025)

Project site

Key project data

Project Reference Number P.3121 - A range of major roadworks in the Sampierdarena port area
Status
Total cost 166,850,628.08€
Activities Works underway
Timeline Start of works date October 2021
Projected completion date December 2025 (Completion roadwork infrastructure West Sampierdarena Basin – San Benigno: September 2025)
Contractor Impresa Pizzarotti & C S.P.A.